Caledonia Bar Strip-Out and Refurbishment

Caledonian Bar hero image

Client: Caledonia Bar
Duration: 6 Weeks
Completed: June 2024
Location: Glasgow International Airport

Project Overview

To deliver the full strip out and refurbishment of the existing Caledonia Bar within Glasgow Airport. All works were carried out within a live, security-controlled Airside airport environment, requiring detailed planning, coordination with stakeholders, and strict adherence to operational and safety requirements.
Scope of Works

The project included:

• Full strip out of the existing bar, including fixtures, finishes, and redundant services
• Refurbishment and reconfiguration of the main bar area to enhance layout, flow, and customer experience
• Manufacture and installation of bespoke joinery incl. bar units and feature elements
• Upgrades to customer-facing areas to align with refreshed branding and improve overall look and feel
• Refurbishment of associated facilities to enhance overall passenger experience
• Installation of new flooring and full internal redecoration
• New lighting installation to enhance ambience and functionality
• Alterations to small power installations to suit the revised layout and equipment requirements
• Coordination with airport operations and compliance teams

Challenges & Outcomes

The challenges and outcomes included:

• Live airport environment: Strict logistics management and phased works ensured no disruption to surrounding operations.
• Bespoke joinery elements: Early design coordination and off-site manufacture ensured quality and programme adherence.
• Programme management: Efficient sequencing and proactive coordination enabled completion within the 6-week programme and on budget.
• Successful transformation into a modern, high-quality bar environment.
• Enhanced customer experience through improved layout, lighting, and finishes.
• High-quality bespoke joinery aligned with branding and operational requirements.
• Minimal disruption to airport operations and strong safety performance.
• Positive feedback from airport stakeholders.